Rue inondée à Liberté 6
Detailed report sheet

ONAS
Khountou score
Response rate
89%
Average processing time
2.1 days
Published responses
312
Reports followed
276
- Status
- Resolved
- Priority
- Medium
- Category
- Flooding
- Location
- Liberté 6, Dakar
- Report date
- 19 March 2025 – 02:21
- Views
- 23
- Followers
- 2
- Resolution time
- 5 days
- Reference
- #ONAS-2025-1960
Main photoReport summary
Rue inondée à Liberté 6. Les riverains signalent la situation depuis plusieurs jours et demandent une intervention rapide.
Le signalement a été transmis à ONAS via la plateforme Khountou.
Report timeline
Report received
19 March 2025 – 02:21
On-site inspection by the ONAS team
19 March 2025 – 05:21
Intervention by the ONAS team
20 March 2025 – 02:21
Problem solved and area cleaned up
24 March 2025 – 02:21
Precise location
Liberté 6, Dakar
Liberté 6, Dakar
Observed issues
- Écoulement anormal constaté sur la voie publique
- Riverains gênés depuis plusieurs jours
- Risque sanitaire pour les enfants du quartier
- Signalements répétés sans intervention durable
Response from the administration (ONAS)

Nos équipes sont intervenues sur place et la situation a été rétablie. Nous remercions le citoyen pour son signalement.
Corrective actions taken
- Constat sur site par les équipes techniques
- Intervention sur l’ouvrage concerné
- Nettoyage et sécurisation de la zone
- Information des riverains
- Suivi post-intervention
Photos / evidence
Similar reports
- 1.Inondation récurrente à Rufisque
19 May 2025 – In progress
- 2.Rue inondée à Diamaguène
06 May 2025 – Resolved