KHOUNTOU.SNEvery citizen, an inspector

Branchement en attente depuis 4 mois à Grand-Yoff

Detailed report sheet

SENELEC

SENELEC

Khountou score

82/100Excellent
  • Response rate

    84%

  • Average processing time

    2.8 days

  • Published responses

    287

  • Reports followed

    142

Status
In progress
Priority
Low
Category
Connection delay
Location
Grand-Yoff, Dakar
Report date
9 July 2024 – 21:43
Views
22
Followers
2
Resolution time
In progress
Reference
#SENELEC-2024-1442
Branchement en attente depuis 4 mois à Grand-YoffMain photo

Report summary

Branchement en attente depuis 4 mois à Grand-Yoff. Les riverains signalent la situation depuis plusieurs jours et demandent une intervention rapide.

Le signalement a été transmis à SENELEC via la plateforme Khountou.

Report timeline

  1. Report received

    9 July 2024 – 21:43

  2. On-site inspection by the SENELEC team

    10 July 2024 – 00:43

  3. Intervention by the SENELEC team

    10 July 2024 – 21:43

Precise location

Grand-Yoff, Dakar
Grand-Yoff, Dakar

View on the map

Observed issues

  • Coupures plusieurs fois par jour
  • Appareils électroménagers endommagés
  • Commerces contraints de fermer plus tôt
  • Aucune information préalable des usagers

Response from the administration (SENELEC)

Le signalement a été pris en charge par nos équipes techniques. Une intervention est programmée dans les prochains jours.

View the full response

Corrective actions taken

  • Constat sur site par les équipes techniques
  • Intervention sur l’ouvrage concerné

Photos / evidence